Go-Live Checklist, Personal Training OS v1.0

Artifact: Phase 6 (Release) · Owner: Primary User · Gate: exits at G6 (Released & backed up) · Date: 2026-07-05

The go/no-go gate before real use. Everything must be ✅ (or consciously waived) before declaring v1.0 live. Timed to be usable for race week, 25 to 26 Jul 2026.

Pre-go-live (readiness)

# Item Status
1 V&V complete, G5 signed, baseline tag vv-accepted ✅ Done
2 Release notes / CHANGELOG published (release-notes.md) ✅ Done
3 Backup/recovery runbook exists (backup-recovery-runbook.md) ✅ Done
4 First real backup taken and logged (runbook §5), proves the procedure end-to-end ✅ Done, the TC-19 export (Markdown & CSV, subpages) serves as the first backup; logged
5 Notion plan confirmed, 2 members (Primary User + Secondary User) covered / seats procured ✅ Done, existing active plan already covers 2 members (predates this project)
6 Secondary User onboarded (has access to the OS page) ✅ Household workspace member
7 Deferred scope communicated (no live sync yet, expectations set) ✅ (release notes). Accurate at go-live 2026-07-05; live sync subsequently added in Increments 2-3

Go-live

# Item Status
8 Declare v1.0 live, start logging real sessions (stop using it as a test bed) ✅ Live 2026-07-05
9 Tag the released baseline v1.0 (signed) ⬜ via signed tag (command below)
10 Seed the immediate race-week plan (Example 5K 07-25, Example Half Marathon 07-26 already in Races) ✅ Races seeded

Post-go-live (hypercare)

# Item Status
11 Use daily through race week; capture any friction as issues (not silent workarounds)
12 After race week: hold Phase 7 retrospective / lessons learned ✅ Done, retrospective written 2026-07-09 (ahead of race week), with the full Phase 7 closure set (benefits realization + post-implementation review); project closed at G7

Open decisions, CLOSED at release (2026-07-05)

  • A, First backup: ✅ the TC-19 export serves as the first backup (logged in runbook §5).
  • B, Notion seats: ✅ existing active plan already covers 2 members, no procurement needed.
  • C, Automation revisit:Garmin integration chosen as the first automation to evaluate, starting immediately after v1.0 lands (feasibility/discovery of the deferred sync work). Outcome (2026-07-05): built and live. Garmin activities and wellness (Increment 2a/2b), Withings weight (2c), and hockey auto-scheduling (Increment 3) all shipped and run on a daily 06:00 sync.

G6 sign-off

Role Name Decision Date
Delivery Manager / PO Primary User APPROVED, Released & backed up 2026-07-05

Signature: authenticated by the SSH-signed release commit that records this and the signed v1.0 tag. Verify with git tag -v v1.0. Next increment: Garmin integration evaluation.

Update (2026-07-05): the Garmin evaluation shipped. Garmin activities and daily wellness (Increment 2a/2b) and Withings body weight (2c) are live, and hockey games auto-schedule into Training Sessions (Increment 3), all live and running on the daily 06:00 scheduled sync since 2026-07-05. These increments carry operational evidence only; the G5 20/20 + 7/7 UAT attestation above covers the v1.0 baseline.